Objective set by IT
Get the number from operations, expressed in shifts. A technically achievable target that does not match production tolerance is the wrong target.
Twenty checks on whether a manufacturer could resume production after losing its systems, measured in shifts rather than days.
In a manufacturing business the recovery objective should be expressed in shifts, not days, because that is the unit in which the cost accumulates.
Most recovery plans are written by IT and describe system restoration. The useful version starts from what production needs to run and works backwards.
Operations director and CIO jointly
Infrastructure and application owners
Plant management
Tick only what you can genuinely evidence today. An item you intend to do is not an item you have done, and scoring yourself generously here only produces a comfortable number and an uncomfortable project.
Set by the business, not by IT.
Whether the mechanism exists and functions.
The only thing that converts a plan into a capability.
The half the plan usually omits.
These bands are deliberately blunt. The middle band is where most organizations honestly sit, and it is a perfectly reasonable place to proceed from — provided the gaps are written down with owners rather than carried as optimism.
Do not proceed yet. More than four in ten items are unaddressed, and the ones that fail here are usually the foundational ones that make everything after them harder.
Proceed on a defined scope, with the outstanding items written into the plan as risks with owners and dates. This is the most common honest position.
The remaining gaps are small enough to handle during delivery rather than before it. Confirm the unticked items are genuinely minor rather than simply unexamined.
Your score highlights automatically as you tick items above. Nothing is saved, sent or tracked — refreshing the page clears it.
The four items below are the ones whose absence causes the most trouble downstream. If your unticked items include any of these, they are worth addressing before the rest.
Get the number from operations, expressed in shifts. A technically achievable target that does not match production tolerance is the wrong target.
Schedule it. Every organization that does this properly finds a dependency nobody mapped, and finding it on a planned Saturday is cheap.
Rewrite for somebody tired who did not build the system. Test by having a different engineer follow one.
Name the person. Late declaration is the most common cause of avoidable extended downtime.
We will assess your current position against the objectives operations actually needs, and facilitate a rehearsal with plant management present.
Twenty checks before a physical count, so the adjustment tells you something rather than merely reconciling a number.
Twenty checks on whether plant data can be trusted to inform costing, planning and margin decisions.
Describe the situation in your own words.